Board vote clears the way for city demolition of Berkman II

Chief Administrative Officer Brian Hughes is “fairly confident” the unfinished  Downtown high-rise will come down in February.


The unfinished Berkman Plaza II high-rise Downtown at 500 E. Bay St.
The unfinished Berkman Plaza II high-rise Downtown at 500 E. Bay St.
  • Government
  • Share

A decision by the Jacksonville Building Codes Adjustment Board on Jan. 13 allows the city to take over the demolition of the Berkman Plaza II high-rise Downtown.

Officials consider the unfinished building at 500 E. Bay St. a public safety hazard.

The board voted 6-0 to deny building owner PB Riverfront Revitalization of Jacksonville LLC’s appeal of the city’s condemnation order. 

The board has deferred the issue three times since October to give a PB Riverfront and its subsidiary more time to address issues that the company says caused repeated delays of a planned implosion.

That position changed after the Jacksonville City Council voted unanimously Jan. 12 to approve Mayor Lenny Curry’s $1.2 million emergency appropriation to pay PB Riverfront’s demolition contractor, Pece of Mind Environmental Inc., to finish its work.

City Chief Administrative Officer Brian Hughes speaks to the  Jacksonville Building Codes Adjustment Board on Jan. 13.
City Chief Administrative Officer Brian Hughes speaks to the Jacksonville Building Codes Adjustment Board on Jan. 13.

City Chief Administrative Officer Brian Hughes said Jan. 14 the board action will allow the city to move “very fast.”

“So, immediately tomorrow (Jan. 14) we’re going to finalize a contracting process, and we have talked to the company about prospective dates,” Hughes said after the meeting.

Because the city considers Berkman’s structural condition a public safety risk, the contract with Pece of Mind will be an emergency procurement. 

Hughes said he’s “fairly confident” they can get the job done in February.

In a letter sent Jan. 6 to city Director of Community Affairs Charles Moreland attached to the bill, Pece of Mind President Steve Pece referred to a payment dispute with the Berkman II developer/owner.

Pece of Mind filed a construction lien against PB Riverfront on Jan. 10 that claims the building owner has neglected to pay $1,574,560.22 of a $1,923,650 bill.

During the Jan. 13 meeting, city officials said subcontractor Controlled Demolition Inc. also is owed $178,642 by PB Riverfront. 

Hughes said the city received correspondence Jan. 13 from the project’s first contractor, Arwood Inc., similar to those from Pece of Mind and CDI, but he was unable to say if it dealt with money owned.

The Jacksonville Building Codes Adjustment Board voted 6-0 to deny building owner PB Riverfront Revitalization of Jacksonville LLC’s appeal of the city’s condemnation order.
The Jacksonville Building Codes Adjustment Board voted 6-0 to deny building owner PB Riverfront Revitalization of Jacksonville LLC’s appeal of the city’s condemnation order.

Safety issues

Pece of Mind outlined safety concerns in the event of extreme weather because of the building’s partial demolition that began in the summer. 

In August, Pece of Mind halted a manual tear-down because of structural and safety concerns and sought city approval for an implosion.

Pece warned the city that his company would end the contract and undo much of the implosion preparation work if PB Riverfront’s account is not brought current.

“This is a unique situation since we had to weaken the Berkman II structure to prepare it for the implosion and the building is only rated for 130 MPH wind load,” Pece wrote. 

“The weakened state of the building is only meant to be temporary, and I can’t predict nor guarantee the structural integrity of the building in the event of a significant weather event.” 

During the meeting, Building Code2 Adjustment Board member and licensed structural engineer Tamara Baker said photographs of the partially demolished Berkman do “not depict conditions that are indicative of complete structural integrity.”

Baker is CEO of Baker Design Build.

She also referenced a structural engineering report received by the city that prompted the August work stoppage. It warned weathered tension cables could cause more “pancaking” or collapse of Berkman floors 15 to 18.

“I can tell you that the existing condition of the building does not meet 130 MPH wind flows,” Baker said. 

Beeler’s response

PB Riverfront and development company Jacksonville Riverfront Revitalization co-manager Park Beeler said the city did not give Jacksonville Riverfront Revitalization “reasonable time” to acquire the additional liability insurance requested by CDI. 

He said the company had to deal with the contractor’s tight schedule and mitigate dust risk to the nearby Maxwell House coffee plant and adjacent The Plaza Condominiums at Berkman Plaza and Marina.

After the vote, Beeler said his company shares the goal of bringing the Berkman II down safely but will weigh its legal options. 

PB Riverfront and development company Jacksonville Riverfront Revitalization co-manager Park Beeler.
PB Riverfront and development company Jacksonville Riverfront Revitalization co-manager Park Beeler.

“Essentially, what they are doing is usurping our right to manage our business under our contract,” Beeler said. 

According to Beeler, the development company’s contracts with Pece of Mind and CDI are active and PB Riverfront would consider lawsuits if the contractors execute contracts with the city. 

Beeler said he is concerned the city’s intervention could go further.

“Our biggest concern is that the city essentially uses all of this as a tactic to take title the property,” Beeler said. 

Hughes said Jan. 12 that the developer would retain ownership of the Berkman II property. 

However, the city could issue a lien to require Jacksonville Riverfront Revitalization cover the taxpayers’ demolition cost.

Beeler said, despite the board’s ruling, Jacksonville Riverfront Revitalization intends to finish the liability insurance purchase in hopes of imploding it independently.

“Until today this owner had never disputed that it was an unsafe structure, which is what the city cited him for,” Hughes said. 

“We let this protract out because he continued to promise on delivery of doing the demo. We were very open to giving him every opportunity.”

Hughes said the secondary benefit of speeding up the implosion is removing a Downtown riverfront building that has been a blight to the area’s appeal and economic development for nearly 14 years. 

Work on the Berkman stopped in 2007 after the collapse of a parking garage that killed one person and injured others.

 

×