Monday marked the 21st day of the scheduled 40-day project to reconstruct the roundabout on Laura Street at the Landing. The concrete subsurface has been completed and workers could start reinstalling the Belgian block cobblestones later this week. After the granite blocks are reset, grout will be placed between them, similar to the construction method at the other intersections along Laura Street north to Hemming Plaza.

 